Rural Street Remodel - Week 2

Days 6 and 7:


Stella hunkers down
Stella Luna hunkers down in her usual spot, just outside the combat zone. What a trouper.
Note dust everywhere


Naked ceiling
Ugly piping tucked up and away between joists; yay


insulation
Insulation goes in everywhere. Note attractive sewer pipe


closet and bathroom
Bath on right, walk-in-closet-to-be on left (compare with last week)

Day 8: Sheetrock! And Living Room Lights!


Sheetrock!
New doorway, looking in



Tigray inspects
Tigray inspects the site


Bathroom door
Bath 'rocked in (but not quite ready to go)


looking southwest
Looking southwest


sewer pipe box
Remember that big black sewer pipe in the corner...?

An add-on for the electrician (or someone like him): 

Ceiling lights for our charming but cave-like living room

Lights above the sofa
Above the sofa


Lights above the bookcase
...and, turning the corner in a perfect "V"

(Between the drywalling and the lighting, Day 8 was quite a day)

Days 9 and 10: Sheetrock, cont'd -- The taper section

West (headboard) wall, Day 9
West (headboard) wall, Day 9


West (headboard) wall, Day 10
West (headboard) wall, Day 10


East wall, Day 9
East wall, Day 9

East wall, Day 10
East wall, Day 10


Closet and bath
Walk-in closet (L) and bath (R) (compare with the end of last week, and three days ago)


ceiling
Ceiling, interesting flaring light effect, Jer


floor
Good thing we're having the floor redone, too




Back to the beginning